This case study explores how SK tes provided a comprehensive data center decommissioning solution for the client, resulting in a 34% higher financial return.

When a large hyperscale data center sought to retrofit their technology infrastructure, they turned to SK tes for support with the urgent removal of their redundant racks. Reacting to the rapid pace of change in today’s digital landscape, they wanted to complete the project quickly, while also recovering value from their retired assets, and ensuring absolute data security. This case study explores how SK tes provided a comprehensive solution to these challenges, resulting in a 34% higher financial return for the client.

Hard-Drive-Destruction_Icons_black_07

72,000
storage servers with varying drives sanitized

Icons_black_11

96% yield
on onsite drive wiping minimized 
the physical handling of drives

Recycling-IT-Assets_Icons_black_08

$4.9 million
generated from
resale of equipment 

Key Challenges with the Colocation Data Center Project

The client faced several key challenges in their decommissioning project:

Large Scale Data Sanitization

The data center held over 72,000 storage servers with drives of varying capacities (4TB, 8TB, and 10TB) 
that needed to be sanitized before removal. Ensuring that no data left the facility was crucial.

Logistical Constraints

Operating within a COLO (colocation) environment, the client had limited access windows for dock 
and staging areas, complicating the logistics of asset removal.

Stringent Security and Compliance Requirements

The client needed to meet strict information security standards, including a certified verification 
report of data destruction.

Tailored and fully planned data center decommissioning solution

Through strategic planning and execution, client needs were exceeded, and SK tes effectively addressed the client's requirements, resulting in enhanced security, operational efficiency, and financial returns. Here are key steps that were meticulously planned for this decommissioning project:

Data center decommissioning solution - SK tes Case Study-1

Results and Benefits Delivered 

Through strategic planning and execution, SK tes effectively addressed the client's 
requirements, resulting in enhanced security, operational efficiency, and financial returns as a part of the data center decommissioning project:

Trust SK tes for your data center decommissioning project

SK tes is a single-source service provider for the full lifecycle management of data center 
equipment. Engaging with SK tes meant that this client had a single company they could 
rely on to undertake decommissioning, data destruction, removal, reuse, and recycling of 
their equipment, reducing vendor management burden and providing an efficient and cost 
effective service.